Moving or re-siting an injection moulding machine: a practical checklist

How to plan, move and recommission an injection moulding machine safely, from preparing the new site to the checks before production restarts.

Injection moulding machine serviced by Immpress

Moving or re-siting an injection moulding machine needs planning in three stages: preparing the new location and the services it needs, making the machine safe and lifting or moving it with the right equipment, then recommissioning it carefully before production restarts. Most problems after a move come from rushed recommissioning rather than from the move itself.

Safety first. Injection moulding machines are heavy and often top heavy. Lifting must be planned by a competent person, using equipment rated for the load, in line with the Lifting Operations and Lifting Equipment Regulations 1998 (LOLER). Electrical disconnection and reconnection must be done by a qualified person.

1. Prepare the new location

  • Floor: check the floor can take the machine’s weight, and plan for levelling and any anti-vibration mounts.
  • Space: allow room to open guards, remove the screw, change moulds and reach the hydraulic tank and electrical cabinet.
  • Access: measure doors, aisles and turning space along the whole route, and check overhead obstructions.
  • Services: make sure the correct electrical supply, cooling water, compressed air and any material handling are ready at the new position before the machine arrives.
  • Ancillaries: plan where dryers, loaders, tool temperature units, robots and conveyors will go.

2. Prepare the machine

  1. Run the machine and note how it is performing, so you have a baseline to compare with after the move.
  2. Remove the mould, purge the barrel and switch off barrel heating so it can cool.
  3. Isolate the machine, then disconnect and label the electrical supply, water and air connections.
  4. Decide with your engineer whether the hydraulic oil should be drained for the move, and make sure stored hydraulic pressure is safely released.
  5. Secure moving parts such as the moving platen, and fit any transport brackets specified for the machine.
  6. Protect the control panel, hoses, pipework and any exposed cylinder rods from impact.

3. Move the machine

Use lifting points or lifting positions specified by the manufacturer, never the platens, tie bars or hydraulic pipes unless they are designed for it. Skates, jacks and forklifts all need to be rated for the full weight, and the load needs to be kept low and stable on the route.

4. Recommission before production

  • Level the machine and fix or mount it as specified.
  • Reconnect the electrical supply and check the motor direction of rotation before running the hydraulic pump, because a pump run backwards can be damaged quickly.
  • Refill or top up the hydraulic oil with clean, filtered oil, bleed the system and check for leaks at every connection.
  • Reconnect cooling water and check flow to the oil cooler and the mould.
  • Test every emergency stop, safety gate and interlock before any production run.
  • Check pressures, speeds and barrel heating against the baseline you recorded before the move.

Moving machines with Immpress

Immpress carries out machinery moving and re-siting and mould shop set up services, alongside our breakdown, servicing and parts work. Because we also service and repair injection moulding machines, we can check them over after the move and set up a scheduled service from day one. Tell us about your move.

Machine moving questions

What should I check after moving an injection moulding machine?

Level the machine, check the motor direction of rotation before running the hydraulic pump, refill and bleed the hydraulics, check for leaks, test every emergency stop and safety interlock, and compare pressures, speeds and heating with how the machine ran before the move.

Do I need to drain the hydraulic oil to move a machine?

It depends on the machine, the distance and how it will be lifted. Agree it with your engineer before the move, and make sure any stored hydraulic pressure is safely released.

Do you move injection moulding machines?

Yes. Immpress carries out machinery moving and re-siting and mould shop set up services, and can service the machines after the move.